Construction 2nd Phase

Well, we had to wait a little longer than a week to get the material. By the time they came in and the weather co-operated it was the last week in August. First the rails and inverters.



A week later they installed the panels.



 Looks like this now.



The power connection goes through the roof



Wire run to the fuse panel



and then outside to the shut off.



To bad it's not hooked up. Well, it was inspected today by ESA and all looks good.
This is necessary before we can hook up to the grid. Hopefully next week we connect in. Then the power meter starts turning. We will then send the inspections to OPA to complete the contract. And then we are in business. 